makrolab | makrolab information bulletin | 001 bulletin date 04 Jul 97 bulletin number 0001040797 This is the first MAKROLAB information bulletin and is edited after the initial phase of the setting up of the laboratory is ending. The setup took more than expected due to last week´s heavy rainfall and low temperatures and unexpected logistical problems connected with the transportation and finalisation of the construction in Slovenia. The phase 1 construction of the lab took 4 days and 320 man hours, a crew of 4 expert workers from Slovenia coordinated the effort. The time schedule was the following: Week from June 16 - 23 Base camp established. Frank Rast and Brian find a trailer, tents set up a week before, with the whole team. Makrolab territory is defined. Sat dishes and video link are operational on June 17. Koeditz is delayed for much more than we thought, but the video link is operational. The console was broken one day after the opening, and we repaired the microfilm reader on Monday, June 23. People have problems with the interfacing at the console, too technical. Will look into this and try to solve some user friendly details. Bottom line is that people don’t like to read the manual, but is there because of the complexity of the whole interface. Brian and occasional helpers align the 1.80m dish, which is still too small for what we intend to do. Inmarsat doesn’t go through. Problems with the antenna, offset dish, receiving unit. - Tuesday, June 24 9:00am truck with the Makrolab systems arrives on Lutterberg 10:00am terrain is prepared for the construction works 11:00am truck has to go to clear customs in Kassel 12:30pm start of unloading procedures, Mr. Fraaz, the farmer on whose land Makrolab is situated helps with his 40 ton tractor and a trailer 2:30pm the truck is unloaded, the material is on the ground 3:00pm start of initial construction works 6:00pm first beams supporting Makrolab are in place 9:00pm the initial construction is in place - the skeleton of the lab starts looking similar to the plans 10:00pm the crew goes to rest, everybody is very tired -Wednesday, June 25 9:00am the working crew starts setting up the supports for the cover membranes 1:00pm the support for the covers is in place 9:00am the Makrolab crew starts preparing systems for SAT receiving. Brian Springer sits in the tent for the whole day, trying to align the dish. Difficult and wet job. 10:00pm the day is over. Makrolab is covered, but not inflated. The generator was running almost for the whole day because of heavy power consumption from the side of the construction crew. Thursday, June 26 9:00am start of finalisation works. Still many details of the covering not solved. Projekt Atol will file an official complaint because of the delay, but the working team is very very fine. 10:00am Internet suddenly starts working again. After two visits of DT; which just told us what we knew from before, that there is an error somewhere, the pipeline just started functioning properly. Good news. Weather really bad. More angry people at the console, because nobody is here to talk to them. Everybody is working, no time for comm. at the moment. Logistics first, comm. later. 6:00pm Makrolab is standing and works. First big shower, some leaks, which are immediately repaired. The construction team came without replacement material for some membrane covering and they had to find some of the same kind in Kassel next morning. Shouldn’t be a problem. Friday, June 27 9:00am final works. The crew from Slovenia leaves. Only the Makrolab team remains. A lot of little work to be done from now on. Expected date of full operationality, July 11, expected date of limited continuous operations July 7. 11:00pm After a whole day of logistical problem solving, the crew goes to rest. Very long day. Saturday, June 28 10:00am Water supply installed and operational. Toilet operational. Galley operational. 3:00pm First real lunch at Makrolab. Galley functional for 6 people. Satisfied. 11:00pm Everybody leaves, but Jurij stays for the first Makrolab night. Sunday, June 29 10:00am Sunday slow start. Bad weather. Sun. Bad weather. A lot of technical set up works in the comm lab. A lot of work around the terrain. Auxiliary power unit installed, but fails in a short circuit. Almost a small fire in the box. APU has to be repaired, because essential. Following the goings on the Mir. Colleagues in trouble, hope everything goes well. Somebody did something bad with Progres. They don´t want to say who... 11:00pm After a dinner at the lab part of the crew moves into Kassel because of operational reasons - storage etc. Part remains. Monday is going to be a difficult day, because Jurij and Bostjan leave Monday night, a lot of things still due. Seats, and a number of invisible details. Monday, June 30 10:00am Cleaning, setting up of chairs, water re-supply. Brian and Marko leave for Enger to get a new communications receiver as a replacement for the one lost by the post or documenta, plus the HF transceiver and antennae. The remaining crew works on the lab supply and operations details and cleaning. 11:00pm dinner 2:00am next day - leaving for Slovenia, only Luka and Brian remain. Tuesday, July 1 - Friday July 4 Comm and internet operations setup. Video link operational. 2 cameras for the moment. Koeditz still has problems with the transmitter. Has to get some parts. The generator never runs. Very well. Frank K. has built the fifth feed up to now. It works well with the 1.8 m dish. But not with the offset. First minutes to write the newsletter. Finally. END of 0001040797